Eight
Tejas to roll out this year; heavily outsourced to private sector
By Ajai
Shukla
HAL,
Bengaluru
Business Standard, 16th Aug 17
Since
December 2013, when the indigenous Tejas fighter was operationally cleared to
join the Indian Air Force (IAF), Hindustan Aeronautics Limited (HAL) has
struggled to establish an assembly line that could build the homegrown light fighter
quickly and cheaply.
With just
three Tejas delivered until this year out of the 20 ordered in 2013, the IAF’s complaint
that the Defence R&D Organisation (DRDO) had taken too long in development
gave way to the charge that HAL was not building the fighter fast enough to
replace the IAF’s retiring MiG fighters.
HAL’s manufacturing
shortfall became even starker last November, when the defence ministry cleared
the acquisition of 83 more Tejas 1A fighters. This successor to the Tejas Mark
1, with four specified capability improvements, is required to enter production
in 2019. This plan hinges on establishing a high-capacity assembly line.
Now,
finally, HAL’s Tejas assembly line in Benguluru is meeting its targets. On a
visit by Business Standard to the Tejas assembly line, HAL chief T Suvarna Raju
has confirmed that eight Tejas fighters will roll off the line this year – the
rated capacity of the assembly line.
Furthermore,
with an additional investment of Rs 1,231 crore sanctioned for enhancing
capacity, the Tejas line is projected to build 10 fighters in 2018-19; and 16 Tejas
Mark 1As each year from 2019-20 onwards.
Thereafter,
the line is expected to build the Tejas Mark II fighter, an advanced variant of
the Tejas with a more powerful General Electric F-414 engine and upgraded
avionics.
Outsourcing
to private defence firms has been key to achieving HAL’s production targets.
“HAL is now focusing mainly on putting together large assemblies that are built
and supplied by private aerospace companies. That has allowed us to speed up
work exponentially”, says Raju.
HAL has
created five “Tier-1” suppliers that each build a part of the Tejas. The front
fuselage is supplied by Dynamatic Technologies Ltd, Bengaluru; the centre
fuselage by VEM Technologies, Hyderabad; rear fuselage by Alpha Tocol,
Bengaluru; wings by Larsen & Toubro, Coimbatore; and the tail fin and
rudder by National Aerospace Laboratory and Tata Advanced Materials Ltd.
Each of
these Tier-1 suppliers sources components and sub-assemblies from lower-order
Tier-2 and Tier-3 suppliers, creating an aerospace industry around the Tejas.
In
addition, a range of equipment is sourced from other private firms that are
emerging as players in the aerospace realm: avionics racks and air intakes from
Lakshmi Machine Works, Coimbatore; electrical panels from Amphenol, Pune; slats
and elevons from Aequs, Belgaum; pipelines from Rangson, Mysore, and precision
mechanical assemblies from Sri Koteswara Cam Systems, Secunderabad.
HAL plans
to eventually outsource 69 per cent of the production of Tejas structural
modules, with just 31 per cent of the work done in-house – consisting mainly of
assembly and equipping work.
A visit by
Business Standard to the Tejas production hanger reveals the most
technologically advanced production line that HAL has ever set up –
significantly more high-tech than the Hawk advanced jet trainer line that was established
with BAE Systems.
The
production jigs, on which Tejas components are fabricated, are calibrated with
lasers to an accuracy of 50-80 microns (one micron is one-thousandth of a
millimeter). This ensures repeatability, which means that every component
coming off a jig is precisely the same, and can be switched across aircraft.
There are
also robotic machines to drill the thousands of holes that are required in each
Tejas’ carbon “skin”. These robots drill in two days what manual drillers
earlier took two months to do.
“It earlier
took us 19 months to build a Tejas, from start to finish. This is now down to
11 months, and we will be building each Tejas in nine months by September this
year”, says Raju.
HAL’s plan
for expanding Tejas production to 16 fighters per year involves establishing a
second assembly line. This has physically replaced the Hawk trainer line that
is close to completing delivery of its orders.
The cost of
Rs 1,231 crore is being half-funded by HAL, with the IAF and navy picking up
the tab for the other half.
Tejas production schedule
Year
|
Production
|
Cumulative
|
Configuration
|
Upto March 31, 2017
|
3 Tejas Mk 1
|
3 Tejas Mk 1
|
IOC configuration
|
2017 – 2018
|
8 Tejas Mk 1
|
11 Tejas Mk 1
|
IOC configuration
|
2018 – 2019
|
10 Tejas Mk 1
|
20 Tejas Mk 1
|
5 single-seat IOC
4 twin-seat IOC
1 (spare capacity)
|
2019 – 2020
|
16 Tejas Mk 1A
|
20 Tejas Mk 1
16 Tejas Mk 1A
|
|
2020 – 2024
|
67 Tejas
|
20 Tejas Mk 1
83 Tejas Mk 1A
|
|
2024-25 onward
|
Tejas Mark II
|
(IOC: Initial Operational
Configuration)
Thank you Ajai. Indigenous capabilities have been largely ignored for larger items between tour pasand netas and import pasand forces. Hopefully at least now, IAF will stop looking at desi maal as Tata cars and hanker for a second-rate aging platform like the single engine Saab 9-3 (anyone who has owned one will testify to the complete lack of reliability and of course, looks).
ReplyDelete- Anon. Coward, ex-Armchair Marshall.
When involved with ATF program the teams were told that the plane has to have stealth , to quietly creek in enemy territory and precisely bomb enemy targets. If the opposition responds by scrambling some planes to have the ATF with best possible AESA long range radar and equipped with long range air to air missiles which can shoot down enemy planes. The best stealth plane today is B2 bomber which has sensors to show radar coverage and it flies smartly between that in a zig zag route with active jammer that essentially blocks the radar. Why was SR 71 not ever shot down and so is F15 eagle never ever shot down , the real reason is speed and thus it is essential to have speed in the fighter. Tejas can go with GE 414 EPE engines and and carry 5500 to 6000 liters of fuel and have a suffice to range , small enough with composite structure to get in enemy territory precisely bomb the targets and then much lighter with half the fuel gone and bombs gone can supercruise with 78 KN of dry thrust and do sustained super cruise and if required can use after burners for a minute or less and safely return home can shoot down any enemy planes coming close to it. I still believe they should be used a wolf pack of 5-6 planes accompanied by high end fighter like Rafael or F35. I am happy that jaguars are fitted with AESA radar and it is matter of time Tejas comes up with AESA radar and 28 sensors integrated. I was similarly happy that hacks are turned into super hawks and have a very modern display screen.the same technology would come to Tejas. Let someone be subcontracted to built this part and all part come in a modular sections with preinstalled wires with plugs and piping already made. This would speed up installation and would make reapairs very easy as they can change the unit and the section can later be re inspected and repairs be made. HAL is good at integrating which it should do so and roll out a plane every three months so that 12 x 4 planes that is 48 planes be rolled out. Start manufacting all components , ask GE to make engines in Bangalore , ask Ella to make radar in India and each and every part made by some private contractor with very strict quality control and time frame the way they run apple assembly in china or intel assembly in Penang. Make at least six hundred planes as they would be cheap to upgrade and maintain that costly war birds from other manufacturers which can be assigned for their selected roles. I am here not talking of air superiority but air dominance.
ReplyDeleteThis would be ideal, but this kind of capability won't come in our country for a while, not in our generation at least. But eventually it will... Where we have the capabilities to demand investment of such magnitude by elta or GE..as of now we don't have that kind of defence industrial complex....not even close....it takes decades of govt policies.... And wars (without foreign OEM support) to actually develop stuff.....
DeleteWe're a country with chalta hai attitude, we don't act, we REACT!!!
Till we don't make stuff on our own, we will always be beggars with second grade technology.
The cutting edge technology that we get from US or Russia isn't the best that they use...its degraded. The good news is that Pakistan and China to some extent also uses the same, but these days China has got really ahead with their indigenous development...(we may make fun of it...but they are getting there)
We on the other hand are really happy buying stuff with Zero tech transfer...not a good way to become a super power!!
I am sure Pvt company involvement will boost it, MoD need to allow Pvt concerns Research and develop in Fighter jets, submarines and Torpedoes and Longer Ranger Bombers Aircraft.that will achieve a greater heights in Make in India.
ReplyDeleteIt is good to use Tejas line finally moving .
ReplyDeleteThis product is incredible .
It has research technology development and product development all in one single project .
Elsewhere like in US we could have DARPA/NASA doing research , then two companies making prototypes fir technology demonstrators, finally one flying !
I do hope this small machine does have all modern electronics like MAWS , IRST over a period of time.
None of these technologies existed when Tejas was defined.
After Dhruv's success , LCH, Tejas , ATAGS seem to heading towards a success.
Maybe fundamentals were missing in IJT, Arjun. We need to study the causes & rectify.
Will Pvt Company manufacturing front fuselage, do the whole fitting out like radome, radar, cockpit or only manufacture the bare shell which will be fitted out at HAL?
ReplyDeleteThank you Ajai! A few pictures of the assembly line would have also been great. One question- where are the 20 FOC standard Tejas Mk1 fighters in the table? You listed 20 Tejas Mk1 IOC fighters and then immediately went on to the 16 Tejas Mk1A fighters for the fiscal year 2019-2020. Weren't 16 Tejas Mk1 FOC fighters supposed to be built for the IAF since 20 FOC standard Tejas Mk1s had already been ordered prior to the 83 Mk1As?
ReplyDeleteThe production time lines are so far into the future that you wonder if the world will still exist, by the time enough Tejas numbers are ready to fight in a war. I guess 6th gen aircraft will be actively flying when Tejas MkII takes to the skies.
ReplyDeleteThat's 8 in less than 8 months left in this financial year.
ReplyDeleteThe SR71 was a reconnaissance plane. It couldn't do MACH 3 at the kind of altitudes that a fighter-bomber has to fly to perform its job. This is not to discount engine power. But TEJAS is a small bird without large internal fuel stores. If you go full load out on it or any other warplane, super cruise, stealth, super manoeuvrability and all that jazz just isn't going to happen.
ReplyDeleteMisleading headline sir. A more accurate one would have been that it is on track to achieve full production capability of 8 for 2017-18
ReplyDeleteSupposed to be 20 Mk.1 IOC-II, Mk.1 20 FOC, and 83 Mk.1A. Total 123.
ReplyDeleteMissing 20 Mk.1 FOC in your list.
Good to know HAL is learning from its mistakes by off loading most of the manufacturing to other companies and concentrating on assembly.
ReplyDeleteThey should have learnt this from Boeing if they have studied their model of working. Waste of a long time and money.
Why Indian baboos take so long to understand simple things of life.??