USS Gerald R Ford, the US Navy's latest carrier, the first to field an EMALS launch system
By Ajai Shukla
Business Standard, 7th Nov 16
The navy has made its choices. When INS
Vishal, the Indian Navy’s second indigenous aircraft carrier enters service, it
will be a technologically cutting edge warship, on par with the world’s most
advanced carriers.
The navy’s finalised specifications include
nuclear propulsion, a catapult launch system based on the new US
“electro-magnetic aircraft launch system” (EMALS) and the capacity to embark 55
combat aircraft.
But advanced technologies also mean delay.
Naval planners, talking anonymously to Business Standard, say INS Vishal will
not enter service before 2030, and might take as long as 2035 to join the fleet
as India’s third operational carrier.
Already, the navy faces six years of delay
in the first indigenous carrier, the 44,000-tonne INS Vikrant, which Cochin
Shipyard Ltd was supposed to deliver in 2015. Until the Vikrant is commissioned
in 2021, the navy will operate just a single carrier --- the 45,000-tonne INS
Vikramaditya, built in Russia and commissioned in 2013.
Yet the navy’s decision is clear --- delay
is acceptable, but INS Vishal must pack the power needed to effectively
dominate India’s extended area of operations. Over the years, the navy has
defined this as extending across the Indian Ocean, from the Strait of Hormuz in
the west, to the Malacca Strait in Southeast Asia.
To dominate this swathe of sea, the navy believes
the Vishal would need at least 55 aircraft on board. These will include two fighter
squadrons, electronic warfare (EW) aircraft, airborne early warning (AEW)
aircraft to monitor and control airspace, and helicopters for special
operations, anti-submarine warfare and communications duties.
Given the capability-to-weight thumb rule
of 1,000 tonnes of aircraft carrier needed for each aircraft embarked, INS
Vishal would have to be about 60,000 - 65,000 tonnes. To propel such a carrier
at a sustained 30 knots (over 55 kilometres per hour), a nuclear propulsion
system has been considered inescapable.
India does not yet have a nuclear
propulsion system suitable for an aircraft carrier. The 83 Megawatt (MW) nuclear
reactors designed for the Arihant-class nuclear ballistic missile submarines
(SSBNs) are inadequate, since an aircraft carrier requires several times more
power than an SSBN.
Developing a new, purpose-built reactor
remains an option, but planners could also attempt to modify the 540 MW nuclear
reactors that India has developed for commercial power generation.
The navy has extensively debated the question
of nuclear propulsion. Opponents of nuclear propulsion point to the Royal
Navy’s 65,000 tonne Queen Elizabeth II, slated to be commissioned in 2017,
which will be powered by Rolls-Royce MT30 gas turbines. Proponents of nuclear
propulsion argue that India’s carriers would require more electrical power,
since these would launch aircraft with the power-intensive EMALS system.
Even so, India’s carriers would be significantly
smaller than the US Navy’s 95,000 tonne Enterprise-class; and the new 100,000
tonne Gerald R Ford-class supercarriers that embark 90-100 aircraft.
“We have conveyed our choice. Now the
government will decide. An aircraft carrier has huge financial implications,
with large annual outlays during construction and even while it is in service.
So the government will understandably consider the choices carefully. And that
means delay”, says a senior naval planner.
The government’s decision will be
complicated by recent reductions in the naval budget. This year, allocations to
the navy are down to just 14.55 per cent of the defence budget, from 18 per
cent in 2012-13. Defence experts opine that, given the navy’s growing role and
the cost of capital warships, an 18 per cent allocation is unavoidable.
Yet, in the wake of the Uri attack, a
high-level empowered committee that visited Russia for emergency purchases of
military equipment bought mainly army weaponry. The admirals worry that the
current focus on tactical skirmishes with Pakistan on the Line of Control might
shift focus from the strategic, long-term need to bolster the navy.
As Business Standard first reported (July
17, 2015, “India specifies 65,000-tonne
aircraft carrier, with catapult”) the navy last year specified INS Vishal’s
approximate weight while seeking consultancy assistance from global
shipbuilders in designing the carrier. But that request was silent on several
key questions --- including nuclear propulsion and EMALS. Nor was there a completion
date.
Another crucial question to be decided is
what aircraft INS Vishal will embark. The MiG-29K, which were bought from
Russia for the Vikramaditya and Vikrant, have limitations that are still being
ironed out. Nor is the Naval Tejas light fighter making significant headway.
That opens the door for two bigger fighters
that already fly off aircraft carriers: the French Rafale, already procured
from Dassault for the air force; and Boeing’s F/A-18E/F Super Hornet, the
world’s premier carrier-borne aircraft. With EMALS technology chosen for INS
Vishal, the US fighter has a slight edge in this race.
NSR says ---
ReplyDeleteIndia needs three aircraft battle groups...
One for East...One for West...One in drydock undergoing refit and repair and replenishment...
They must immediately build exactly same prototype with conventional propulsion...
They first need to build 6 SSBN and 6 SSN to get experience on nuclear reactors...
Only then India shoud go for a nuclear aircraft carrier..
Security will be at risk...go ofor an immediate same aircraft carrier...
2035 is too far away to wait for the second carrier!! Who knows how the world will look like then...
ReplyDeleteRegarding aircrafts, in 2035, all other powerful navys will be on the verge of decommissioning F-18, rafale or MiG-29k( US have already announced that). These aircrafts may not survive against 5th gen capabilities of stealth& huge data processing, which gives them obvious upper hand in long ranges. So to flex muscle in oceans, is not a dedicated 5th gen carrier launched aircraft project necessary?
ReplyDeleteIn the meantime another conventionally powered follow on to the INS Vikrant should be built.
ReplyDelete@ colonel ajai shukla, have you ever attended SOFEX(special ops forces exhibition), i think yes, can u let us know what kind of mechanism they use, as itsclaimed that Hezbollah's got chinese drones/rockets from SOFEX
ReplyDeleteThis is yet another example of wasting precious resources on a hugely expensive to buy and operate nuke powered carrier. Imagine how many corvettes and OPVs or for that matter submarines could have been bought for the cost of one CVN. Sadly, the bigger the IN becomes, the dumber it becomes since it desperately wants to be seen as a 'big navy'.
ReplyDeleteF35 naval version is an option too. Else Rafale will do, fa18 failed our evaluation.
ReplyDeleteby then china will be sitting on our arse -- lets forget it
ReplyDeleteSir, is this going to be just one sole carrier? Or 2-3 follow on carriers of this class? Surely, they won't stop at one will they?
ReplyDeleteNothing wrong with a CVN, except we cant wait for 2035 for a 3rd carrier. Parthi89 correctly notes we need additional Vikrant class, minimum 2-3. C hina's 2nd carrier is due 2021 (60,000-tons) so Vikrant in 2021 is till okay, but afyer China gets its #2 CV, it is going to speed up.
ReplyDeleteDalip, if you look at what China is upto in the Indian OCean, they have already surrounded us while we keep dreaming. They have nval basing facilities in Gwader, anytime access to Karachi, are building a new port for Sri Lanka, communications facilities off Andaman; increasing investment in Burma, and are piling into Bangladesh. They already have their first naval facility near Suze (Djibouti, where they will build a proper naval base). They are doing their best to get US out of Philippines, and will succeed, because they have tens of billions of dollars to invest in each and every country they want. They are already the biggest investors in Africa, and are moving into South America big time.
Victor, F-16 and F-18 were never in the running: IAF says they were tested, but there was no intention to buy them no matter what. Hornet F-18/E/F looks the same as the earlier Hornet, it is a completely different aircraft that will serve until 2055 at least. Australia has just bought a new batch, and Canada is delaying its F-35 and will buy more F-18s. Problem with Rafale is that French have never been honest on its real price: life-cycle is $330-million each. We're paying $250-million for each Rafale and that is not true life-cycle either.
ReplyDeleteAs Colonel Shukla has been saying over-and-over again for years, ur procurement policy makes NO sense at all for just about anything. Now a US mag - I think its defensenews.com - has come out with the 1st realistic figure for how messed up we are; giving a backlog of $400-bil worth of weapons. I suspect they have used Col. Shikla's estimates; except when he made that estimate I discussed with him it is more likely $600-billion we need to meet TODAY's shortages. We've let modernization go for over 25-years