By Ajai Shukla
Business Standard, 26th Dec 2014
A major
trend in India’s defence spending has been the navy’s growing share, which has risen
from 4 per cent of the defence allocation in the early 1960s to a high of 18.12
per cent in 2012-13.
This is
seen worldwide as evidence of an increasingly muscular profile in the Indian
Ocean region, where India will not just protect its 7,517 kilometres of
coastline and 1,197 islands, but function as the premier maritime power that secures
freedom of navigation over 6,000 kilometres of international sea lines of
communication (SLOCs) in its vicinity.
Parliament’s
Standing Committee on Defence fears this signal is being diluted. This year, the
navy was allocated just 15.72 per cent of the defence budget, down from 16.79
per cent last year. That amounts to Rs 37,808 crore (USD 5.95 billion).
Unprecedentedly,
the parliament committee has ordered the government to allocate more funds to
the navy.
The
committee says the alarming rise in accidents, including the 2013 sinking of
INS Sindhurakshak --- a frontline Russian Kilo-class submarine --- indicates
the navy needs more money for purchasing modern equipment, maintaining it
properly and training seamen to the required level of skill.
Citing the
“spurt in accidents”, the committee notes: “in most of the cases of accidents,
the cause is either material failure or human error. This implies that either
the equipment and machinery acquired are substandard or there are inadequacies
in training. The Committee feel that the inadequate funding will further
aggravate the condition of Indian Navy and lead to compromises in operational
preparedness. Therefore, it is the absolute necessity to allocate ample funds
to Navy under intimation to this Committee (sic).”
The panel
reveals that the navy is significantly understrength. The report says: “In
2012, [the defence ministry] approved 198 ships and submarines for Indian Navy.
The present force level is 127 ships, 15 submarines and 236 aircraft. There are
presently 14 conventional submarines (including Sindhurakshak) in the Indian
Navy. Most conventional submarines are over 20 years old and are reaching the
end of their service life.”
Worryingly,
this year’s capital allocations, i.e. the funding for new equipment purchases,
will be mostly expended on “Committed Liabilities”, i.e. on annual instalments for
equipment procured during previous years. Of the total capital allocation of Rs
23,832 crore, about Rs 17,313 will be expended on committed liabilities,
leaving just Rs 4,599 crore for new purchases.
The
committee sharply criticises large cost overruns on major warship projects. It
notes that Project 15A, for building three Kolkata-class destroyers, was sanctioned
at Rs 3,580 crore, but eventually cost Rs 11,662 crore, more than thrice what
was initially envisaged. In Project 28, which involves building four
Kamorta-class anti-submarine corvettes, the sanctioned cost of Rs 3,051 crore rose
to Rs 7,852 crore. The largest overrun was for the Indigenous Aircraft Carrier,
INS Vikrant, which went up almost six-fold from the sanctioned Rs 3,261 crore
to Rs 19,341 crore.
A key cause
of these large overruns has been the MoD’s budgeting methodology, which
involves sanctioning a project at a notional (invariably undervalued) cost and
then arriving at a more realistic figure once the first ship of that project is
physically built.
The
committee has noted that the project cost for INS Vikrant was grossly
underestimated in 2002. In somewhat garbled prose, the report says: “Cost
overrun was mainly due to reasons of cost estimation for [cabinet] sanction in
2002 at a time when (the vessel’s) ‘form & fit’ was still emerging; limited
information on many Aircraft Carrier specific equipment & material due to
inadequate domain knowledge; Equipment costs, emerging technological advances
and new generation equipments in IAC (sic).”
The MoD has
been asked to resolve this issue and apprise the committee.
Infantry is the Queen of battle field it should not be neglected give them better rifles and then proceed in other areas
ReplyDeletePrimitive view. A land incursion or occupation of territory is among the most unlikely scenarios. The relative funding may best be decided by specifying desired levels of preparedness to be achieved say in 2025.
ReplyDelete